Upper Stillwater Dam Slope Stabilization

Location: Duchesne County, UT

Client: Bureau of Reclamation

Duration: 4 months

Contract Value: $550k

This slope stabilization project of abutment of Upper Stillwater Dam was located on a 50 acre area.  The project included installation of double twist wire mesh, cable netting on rock face, drilling and grouting of 24’ rock bolts as well as installation of 600’ of gabion basket. 